Mechanical Contractor Defeats Claim of Fabricator and Recovers $1 Million
The Project involved the installation of a new paper machine and accompanying construction in New York. All of the pipe for the project was provided by an independent fabricator. During the construction, the owner made numerous design changes. The fabricator cited these changes as the reason that its pipe was late. The fabricator filed suit […]